Build a new cable, or renew the old one?

Many operators own a subsea cable from the 1990s. It still works, but it is full. This guide explains when new equipment on the old cable is enough, and when only a new cable will do.

By the UNIFI network team. 6 minute read.

Optical equipment at a cable landing station

THE SHORT ANSWER

Renew when the cable in the water is healthy and you need capacity soon. Build when you need more fibre, a new route, or decades of growth.

622 Mbps
UGARIT 1 capacity when it entered service in 1995
6 Tbps
UGARIT 1 capacity after UNIFI renewed it in 2025
Same cable
No work at sea. New equipment at the landing stations

Why an old cable can carry far more

A subsea cable has two parts. The cable in the water, and the equipment on shore that sends light through it.

The glass fibre in the water does very little. It is a passive path for light. The equipment at each end decides how much data that light carries. That equipment has improved enormously since the 1990s.

So the cable can stay, and the equipment can change. This is what the industry calls an upgrade. We call it Relight.

It works best on shorter systems with no powered amplifiers under the sea. These are called repeaterless systems. With nothing electronic in the water, there is nothing under the sea that goes out of date.

When renewal is the right answer

  • The fibre is healthy. Testing from end to end shows the glass is intact and losses are within limits.
  • You need capacity soon. An upgrade is delivered in months.
  • The budget is limited. You pay for equipment, with no ship, no survey and no new cable.
  • The route still suits you. The landings are where your traffic needs to be.
  • You want a bridge. Renewal can carry your traffic while a new system is planned and built.

When you need a new cable

  • Too few working fibres. Older cables carry few fibre pairs, and some may be damaged.
  • Frequent faults. An ageing cable that breaks often costs more each year to keep alive.
  • A different route. You need a new landing, or a path that avoids a chokepoint.
  • Growth for decades. Ai and cloud demand may outgrow anything the old fibre can carry.
  • Ownership and control. A new system lets you set the partners, the suppliers and the rules from the start.

SIDE BY SIDE

Renewal and new build compared.

Renew the old cableBuild a new cable
What changesEquipment at the two landing stationsEverything. Cable, landings and equipment
Work at seaNoneSurvey, manufacture and laying
Time to serviceMonthsYears
CostA fraction of a new systemThe full cost of a system
Capacity you gainLarge, but limited by the fibre already thereSet by you. More fibre pairs, more room to grow
New route or new landingNoYes
Remaining lifeTied to the condition of the old cableA new design life

IN PRACTICE

We have done both, between the same two landings.

Renewal and new build are not rivals. On one corridor in the Eastern Mediterranean, the owners chose renewal first and a new system second.

Delivered

First, Relight. UGARIT 1

A 239 km cable in service since 1995. UNIFI delivered new equipment at the landing stations in 2025. Capacity rose from 622 Mbps to 6 Tbps, close to ten thousand times more, on the cable already in the water.

In development

Then, Genesis. Ebla (UGARIT 2)

A separate new system on its own route. 240 km, 24 fibre pairs, 31 Tbps at launch and 370 Tbps by design. UNIFI builds it turnkey and is part owner alongside Cyta and Syrian Telecom. Service is targeted for mid 2028, subject to project conditions.

The same approach worked between Italy and Greece. IG 1 was built in 1995. In 2022 it was renewed with 400G technology and extended to Bari, and it carries traffic today.

BEFORE YOU DECIDE

Five questions to ask about your cable.

  • How many fibre pairs are intact today, tested from end to end?
  • How many faults has the cable had, and how recently?
  • How much capacity will you need in five years, and in fifteen?
  • Do the landings still sit where your traffic needs to go?
  • Can you wait years for a new system, or do you need capacity this year?

If the first two answers are good and the last is urgent, start with renewal. If the third answer is very large, plan the new cable now and let renewal carry you until it arrives.

COMMON QUESTIONS

Short answers.

How long does a subsea cable last?

Most systems are designed for about 25 years. Many keep working well beyond that when the cable is in good condition and the equipment on shore is renewed.

Can an old cable carry modern capacity?

Often, yes. The fibre in the water is passive glass. Capacity is set mostly by the equipment at each end, and that equipment can be replaced.

How long does an upgrade take?

Months, where a new cable takes years. There is no marine survey, no cable manufacture and no laying.

When is a new cable the only answer?

When the old cable has too few working fibres, when faults are frequent, when you need a different route or landing, or when demand will outgrow what the old fibre can carry.

Own an ageing cable? Ask us for a Relight assessment.